As the general contractor, DPR Construction leveraged its self-perform work (SPW) expertise and partnership with Digital Building Components to recover a month’s worth of weather delays to the project schedule.
DPR worked with Brave Architecture and The Mathis Group, Inc., to bring recenter to life. The project scope consists of a new five-story 50,573-sq.-ft. mixed-use building complete with a dining room, meeting room, lounge, offices and 62 individual residential units. Outdoor amenities include terraces, porches and a garden roof deck.
DPR’s project superintendent, Brandon Liming, was impressed by the speed of installation. “We were able to dramatically increase production rates to even meet our initial ‘aggressive’ theoretical expectations.”
Liming attributes this success to vigorous preplanning. “Having preparation milestones was the key to success. At every stage, we knew the responsibilities of each crew member—from when the trailer arrived onsite to its departure.”
Working in small groups of two and three, DPR’s eight-person SPW installation team completed the work in 13 days, building on average 2,300 sq. ft. each day—four times faster than conventional building methods and well ahead of the already rigorous projected schedule of 17 days. A variety of trades were able to put their work in place sooner as the result of the accelerated structural schedule.
The design and owner partners were also impressed with the rapid pace of construction, even though recenter had originally been designed using conventional steel. While the initial decision to pursue prefabrication was driven by scheduling considerations, the project’s overall budget also came in at the same cost as conventional steel.